Industry new

The Requirements of Overhead Crane Rail Installation for Steel Structure Rail Beams

The Requirements of Overhead Crane Rail Installation for Steel Structure Rail Beams:

Overhead Crane Rail

(1) The span of the Overhead Crane Rail beam is ≤ h / 500, h is the beam height of the Overhead Crane Rail beam.

(2) the horizontal beam side of the Overhead Crane Rail beam ≤ l / 1500, and net 10mm, l for the beam length.

(3) rail beam vertical direction arch ≤ 10mm.

(4) the center of the Overhead Crane Rail beam on the design of the positioning axis deviation ≤ 5mm, if not meet the requirements, you should adjust the Overhead Crane Rail beam positioning, to install the Overhead Crane Rail.

(5) with the same cross-section of the same cross-section of the beam height difference in the bearing ≤ 10mm, the other ≤ 15m.

(6) with the adjacent column 2 between the top of the Overhead Crane Rail beam height difference ≤ l / 1500, and ≯ 10mm, l for the beam length.

(7) adjacent 2-Overhead Crane Rail beam joint parts, 2 rail beam top height difference ≤ 1mm, center lateral misalignment ≤ 3mm.

CONTACT US

Contact: Bruse Skype:nucleoncranegroup

Phone: WhatsAPP:008618637120986

Tel: 0086 371 65657585

Email: info@nucleoncranegroup.com

Add: Crane Industrial Park, Changyuan County, Henan Province, China