The commissioning of the Mobile Overhead Crane is divided into the following steps

The commissioning of the Mobile Overhead Crane is divided into the following steps

 Mobile Overhead Crane

Mobile Overhead Crane of no-load test, no-load test according to the following procedure and requirements:

(1)   The brake wheel of each mechanism is rotated by hand so that the last axis (such as the wheel axle) can not be stuck when it rotates for a week.

(2)   Trolley walking: the empty trolley walks back and forth three times along the track, when the wheel should not be skidded.

(3)   Empty hook lift: start button box on the ground, i-steel beam Mobile Overhead Crane price, make the empty hook up and down three times, the switch action should be accurate and reliable.

(4)   Drive the electric hoist to the midspan, and the Mobile Overhead Crane walks along the building for two times. In order to verify the housing rack and track, and then walk three times at rated speed, check the working quality of the walking mechanism. When starting or braking, the wheels should not skid, travel smoothly, and the bumper works normally.

CONTACT US

Contact: Bruse Skype:nucleoncranegroup

Phone: WhatsAPP:008618637120986

Tel: 0086 371 65657585

Email: info@nucleoncranegroup.com

Add: Crane Industrial Park, Changyuan County, Henan Province, China